Milestone | Work Package | Delivery | ||
MS1 | Specification of Product | WP1 | M8 | Design document for the requirements and development of chemical solution |
MS2 | Selection of composition and siloxane building blocks | WP2 | M12 | Validation on the choice of functional groups |
MS3 | Feasibility establishment | WP2 | M14 | Go/No Go decision based on establishment of the feasibility of the selected approach |
MS4 | Optimised coating solution | WP2 | M18 | Coating solution with required properties |
MS5 | Optimised coating process | WP3 | M24 | Optimised coating process design and parameters |
MS6 | Performance validation | WP4 | M30 | Application profile efficiency check |